News: Difference between revisions
No edit summary |
No edit summary |
||
Line 164: | Line 164: | ||
{| |
{| |
||
|- style="vertical-align:top" |
|- style="vertical-align:top" |
||
|'''''21.12.2015'''''<br /> HALO has just started for the '''early winter survey flight'''. The flight today probes the early polar vortex and leads into the Arctic around Spitsbergen, to Scandinavia, and back to Oberpfaffenhofen. |
|'''''21.12.2015'''''<br /> HALO has just started for the '''early winter survey flight'''. The flight today probes the early polar vortex and leads into the Arctic around Spitsbergen, to Scandinavia, and back to Oberpfaffenhofen. (Photo by Wolfgang Woiwode, KIT). |
||
|[[File:IMG_0872.jpg|mini|rechts|320px|[[North Flight]]]] |
|[[File:IMG_0872.jpg|mini|rechts|320px|[[North Flight]]]] |
||
|} |
|} |
||
Line 197: | Line 197: | ||
{| |
{| |
||
|- style="vertical-align:top" |
|- style="vertical-align:top" |
||
|'''''18.11.2015'''''<br /> The '''ground-based EMC tests''' have been completed successfully on 17 and 18 November 2015. Short status and planning meetings are scheduled for 25 November 2015 (11 am) and 1 December 2015 (2 pm). The functionality of the IRIDIUM satellite link as high-latitude back-up for INMARSAT has been tested successfully on 23 November 2015 to allow chat funcionality for operators also north of ~70°N.(Photo by Wolfgang Woiwode, KIT). |
|'''''18.11.2015'''''<br /> The '''ground-based EMC tests''' have been completed successfully on 17 and 18 November 2015. Short status and planning meetings are scheduled for 25 November 2015 (11 am) and 1 December 2015 (2 pm). The functionality of the IRIDIUM satellite link as high-latitude back-up for INMARSAT has been tested successfully on 23 November 2015 to allow chat funcionality for operators also north of ~70°N. (Photo by Wolfgang Woiwode, KIT). |
||
|[[File:151118EMCTest.jpg|mini|rechts|320px|[[EMC Test]]]] |
|[[File:151118EMCTest.jpg|mini|rechts|320px|[[EMC Test]]]] |
||
|} |
|} |
Revision as of 12:40, 20 August 2020
06.07.2017 The POLSTRACC Summer Meeting has taken place in Klingenmünster, and latest results on dynamic processes, polar stratospheric clouds, cirrus clouds and chemical processes in the Arctic lowermost stratosphere were presented. The POLSTRACC special issue in the journals ACP and AMT is now open for submissions. |
20.06.2017 The POLSTRACC Summer Meeting is scheduled for 05.-06. July 2017. We are looking forward to discuss the latest results from the POLSTRACC/GW-LCYCLE/SALSA data. |
10.11.2016 After an exciting Science Workshop in Klingenmünster, the scientific evaluation of the POLSTRACC/GW-LCYCLE/SALSA data proceeds. The next meeting is planned for summer 2017 at the same location. |
21.10.2016 After the POLSTRACC/GW-LCYCLE/SALSA Campaign was concluded successfully in March 2016, the first POLSTRACC Science Workshop is scheduled for 09.-10. November 2016 in Klingenmünster, Germany. |
23.03.2016 With the dismounting of the payload completed, this now finally concludes the POLSTRACC/GW-LCYCLE/SALSA campaign. We would like to thank all who have contributed to make this campaign a great success! With the campaign itself completed, the focus of the work will now shift towards the scientific analysis of the data. |
21.03.2016 The HALO Kuratorium (supervisory board) visited on Monday, 21 March the POLSTRACC/GW-LCYCLE/SALSA campaign in Oberpfaffenhofen. With the two proud coordinators Björn-Martin Sinnhuber and Hermann Oelhaf on the ladder. (Photo: DLR: http://www.dlr.de/dlr/desktopdefault.aspx/tabid-10081/151_read-17243#/gallery/22489). |
16.03.2016 HALO science flight PGS_20 was successfully completed today. The flight was particularly tailored to meet the SALSA objectives, with a southernmost latitude of 25°N. A refueling stop in Faro was included on the way back. |
29.02.2016 Gavity waves and a the tropopause structure around a small polar low off the coast of Norway were the focus of HALO science flight PGS_15 that was successfully completed on 29.02.2016. |
02.02.2016 HALO has just returned from science flight PGS_13 that went up to 87°N and included a hexagon pattern around Spitsbergen to probe gravity waves. This concludes the first Kiruna phase of the POLSTRACC/GW-LCYCLE/SALSA mission. |
31.01.2016 With PGS_12 today we finished successfully another 9 hrs HALO science flight. Highlights of the flight were long stretches of PSC observations by the WALES lidar, crossing of the subtropical jet north of Ireland with ozone going down from 900 ppbv to as low as 25 ppbv and high partriculate NOy at the same flight level, and a flight leg under defined constant solar zenith angle conditions for chemistry observations by the mini-DOAS instrument. |
20.01.2016 HALO is in the air again for research flight PGS_08 towards Iceland, Greenland and Spitsbergen. (Photo by Björn-Martin Sinnhuber) |
08.12.2015 The inflight EMC test has been completed sucessfully (see photo by P. Preusse, FZJ). Flight planning for the scientific flights is in progress. |
02.12.2015
All necessary documentation needed for achieving the Permit to Fly (PfF) has been submitted to the Federal Aviation Office (Luftfahrtbundesamt, LBA). The pre-briefing for preparing the EMC flight has been completed today. Count-down plans for a possible flight on 3 or 4 December 2015 have been agreed on. We are now waiting for clearance from the LBA.
03.07.2015
The Critical Design Review of the combined HALO payload for POLSTRACC/GW-LCYCLE/SALSA and WISE has been performed successfully on 23 June 2015, and no major technical problems have been identified. "Design Freeze" is scheduled for 17 July 2015. The finalization of the instrument Interchange Control Documents is scheduled for mid of September 2015 and will be followed by the "Final Critical Design Review" at the beginning of October 2015.
29.05.2015
The Critical Design Review of the POLSTRACC-Payload of HALO is scheduled for 23 June 2015 at DLR, Oberpfaffenhofen.
08.04.2015
The POLSTRACC mission will be presented at the European Geosciences Union General Assembly 2015 (Vienna, 12-17 April 2015) in the AS3.12 Polar Ozone and Polar Stratospheric Clouds Session on Thursday, 16 April.
26-27.03.2015
Flight planning associated to the joint POLSTRACC/SALSA/GW-LCYCLE (PGS) campaigns was exercised at the Mission Rehearsal at DLR-IPA, Oberpfaffenhofen.
13.02.2015
The instrument test integration during the "Stellprobe" (02.-06.02.2015) at DLR, Oberpfaffenhofen was finished successfully. On 05.02.2015, the Preliminary Design Review was performed and the timeline for the mission preparation phase was refined. During the Status Meeting at the same day, logistic aspects of the campaign phases in Kiruna and scientific flight scenarios were discussed. The Mission Rehearsal is scheduled for 26.-27.03.2015 at DLR, Oberpfaffenhofen.
02.12.2014
The "Stellprobe" is scheduled for 02.-06.02.2015 at DLR, Oberpfaffenhofen. In the same week, a Status Meeting will take place at the same location.
13.-14.11.2014
POLSTRACC General Meeting at KIT, Karlsruhe:
Discussion of the timeline, payload, flight operations, certification and logistics of the joint POLSTRACC, GW-LCYCLE and SALSA campaigns. Data products for scientific flight planning are presented and a Mission Rehearsal is planned for early 2015 at DLR, Oberpfaffenhofen.
28.05.2014
POLSTRACC Kick-Off-Meeting, DLR Oberpfaffenhofen
22-23.04.2013
POLSTRACC/ROMIC meeting at KIT, Karlsruhe: The scientific objectives of POLSTRACC/GW-LCYCLE are sharpened and the HALO payload configuration is discussed.